Preconstruction and Planning
Alexis von Hardenberg
Group BIM, Design and
Marketing Manager
Our Preconstruction and
Planning team get involved
in every project once the
invitation to tender is
received . At tender stage
we utilise the following
workflow on all projects.
Scope Review
All tender documents are
reviewed
once
received
so our team has a through
understanding of the scope.
If there is no 3D model we
commence building one.
BIM Common Data
Enviroment
Constructability Review
Detailed
constructability
reviews are carried out of
elements such as substructure,
superstructure, envelope, roof
and internal finishes. This helps
to understand the elements
unique to the specific project
and complete our model to the
appropriate level of detail.
BIM Authoring
Enviroment
Logistics Plans
We produce 3D logistics plans
to help plan the logistics,
specific focus is placed on crane
positions, temporary works such
as scaffolding and access and
egress routes.
BIM Coordination
Micro Build Sequences
Once
our
constructability
reviews are completed we
prepare micro 3D sequences to
detail specific assemblies such
as structural assemblies for
typical floors, envelope buildups,
roof details.
BIM Visualisation
4D Construction Sequence
For our final tender submission
we prepare a fully detailed
4D
construction
sequence
to articulate our proposed
construction methodology and
programme.
BIM 4D Construction
Scheduling