CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Water - 533
(1) PROJECT NAME: WATER / ARDICE WELL REHABILITATION
PROJECT STATUS: Existing in Edmunds
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
The Ardice well pump is located inside a building and requires a crane to pull the well. The
project would consist of removing the column, shaft, and pump and inspecting the pump,
cone, columns, spider bushings, and shafts. The equipment will be rebuilt or replaced. The
well casing will be inspected by video and a copy retained by the City.
(3) PURPOSE OF PROJECT:
X
Extend life of existing infrastructure
X
Replace existing infrastructure
Expand infrastructure
PROGRAM:
Water Projects - 8600
ACCT1#:
042-8600-533-65-03
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
Moved money from 21/22 to 23/24.
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
TOTAL
a. Land Acquisition
b. Planning
c. Design
d. Architecture/Engineering
e. Site Development/Construction
- - 70,000 - - - 70,000
f. Equipment,Vehicles, Etc
g. Contingency
- - 3,500 - - - 3,500
h. Other
i. Project Additions/Changes
TOTAL
- - 73,500 - - - 73,500
(5) PRIORITY:
Timetable
safety concern, hazardous condition, agency compliance, non-funca.
risk
tional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c. X service level mainten.
maintains City desired level of service
2 - 5 Years out
d. service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
Current Year
YEARS
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY26/27
2028-2032
TOTAL
Change in Fuel Costs
- - - - - - - Change in Utility Costs
- - - - - - - Change in Maintenance
- - - - - Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
Ardice Water Treatment Plant.
1) Water & Sewer R&R Fund 042
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
N/A
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works