CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Water - 533
PROGRAM: Water Impact Projects - 8600
(1) PROJECT NAME: WATER IMPACT / RECLAIMED WATER MAIN EXPANSION HICKS DITCH RD
PROJECT STATUS: Existing in Edmunds
ACCT1#:
065-8600-533-67-37
ACCT2#:
ACCT3#:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
This project is the installation of approx. 1000’ of 12” PVC reclaim water main. The extension will supply reclaim water to portions of the North East section of the City. The construction will be by directional bore and open trench from Hicks Ditch Rd. East 1000’.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
X
Expand infrastructure
Project to expand reclaimed infrastructure.
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
TOTAL
a. Land Acquisition
b. Planning
c. Design
d. Architecture/Engineering
e. Site Development/Construction
- - - - 100,000 - 100,000
f. Equipment,Vehicles, Etc
g. Contingency
h. Other
i. Project Additions/Changes
TOTAL
- - - - 100,000 - 100,000
(5) PRIORITY:
Timetable
safety concern, hazardous condition, agency compliance, non-funca.
risk
tional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c. X service level mainten.
maintains City desired level of service
2 - 5 Years out
d. service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
Current Year
YEARS
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY26/27
2028-2032
TOTAL
Change in Fuel Costs
- - - - - - - Change in Utility Costs
- - - - - - - Change in Maintenance
- - - - - Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
CR 44/Hicks Ditch Rd.
1) Water Impact Fee Fund 065
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
N/A
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works