CIP Book FY 2023-27 - Final - Flipbook - Page 70
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Parks & Recreation - 572
(1) PROJECT NAME: PARKS & REC / PICKLEBALL COURTS
PROJECT STATUS: In Earlier CIP - Not in Edmunds
PROGRAM:
7320 Athletic & Recreation Programs
ACCT1#:
010-8600-572-60-22
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
This project would create four Pickleball Courts to be located where the old shuffleboard
courts used to be at the Eustis Service Center. Pickleball is a high trending activity that
continues to grow in popularity, especially among the senior population. Constructing pickleball courts has been a highly requested amenity from the community. Courts to include
lights, posts, nets, benches, and shade provision.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
X
Expand infrastructure
The cost has significantly increased. The budget for the entire project
will now yield two courts. Propose adding lines to existing tennis
courts first to verify use before building courts
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
TOTAL
a. Land Acquisition
b. Planning
c. Design
d. Architecture/Engineering
e. Site Development/Construction
- - - - 90,000 - 90,000
f. Equipment,Vehicles, Etc
g. Contingency
h. Other
i. Project Additions/Changes
TOTAL
- - - - 90,000 - 90,000
(5) PRIORITY:
Timetable
safety concern, hazardous condition, agency compliance, non-funca.
risk
tional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c. service level mainten.
maintains City desired level of service
2 - 5 Years out
d. X service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
Current Year
YEARS
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY26/27
2028-2032
TOTAL
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
Various
1) Sales Tax Revenue Fund 010
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
FRDAP Grant 50/50 match
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Craig Dolan – Director of Parks & Recreation