DOWNTOWN BEAUTIFICATION PROJECT
PARLIER, CA
overlay within the project limits. The end result not only improved
the city aesthetically but also created a safer walkway for residents
to enjoy for years to come.
APC Project Team
Project Manager: Jimmy Brager
Project Estimators: Ross Jenkins and Chris Williams
Foremen: Jose Flores (Project), Felix Hernandez (Concrete) and
Scott McKinley (Structural)
The project involved the upgrading of a threeblock stretch of downtown Parlier.
Project Assistant: Des Hutcheson
The City of Parlier Downtown Beautification project for the City of
Parlier is what we like to call a “Quick Hitter”. The project bid on
March 24, 2022 and the Parlier City Council awarded the project
one week later on March 31, 2022. The contract was executed on
April 15, 2022 and APC went to work on April 21, 2022. The period
from bid to project start was less than a month.
Other Key Personnel: Jose Mata, Alex Flores and Jose Ramirez
WWTP EXPANSION PROJECT
Fresno, CA. APC was excited to be part of the WML team
on the Wastewater Treatment Plant Expansion Project for the
Root Creek Water District. APC subcontracted the civil scope of
work for the site grading, site access road including aggregate
base and asphalt concrete, site aggregate base surfacing and
site concrete. The site grading included 15,752 CY of cut to fill
and 11,456 CY of imported borrow. The site concrete included
4,952 lf of curbing. A total of 7,675 tons of aggregate base and
815 tons of asphalt concrete were placed and finished.
The project consisted of upgrading a three-block stretch of
downtown Parlier. Curb Ramps and crosswalks were added
at three intersections and mid-block planters and a mid-block
crosswalk were also added along with fifteen planter “bulb-outs”.
The storefront sidewalk was to be demolished and replaced with a
combination of concrete sidewalk and decorative red brick walkways,
all while maintaining access to the businesses. New landscape and
irrigation was added at all of the new bulb-outs. Decorative light
posts were also installed, as well as site amenities that included
decorative benches, trash receptacles, raised planters, decorative
tree grates and trench drain grates.
APC Project Team
Project Manager: Jimmy Brager
Project Estimator: Ross Jenkins
Foremen: Brandon Best (Project) and Felix Hernandez
(Concrete)
Other Key Personnel: Val Huerta, Josh Mills, Jose Flores,
Santos Arana, Jose Mata and Jose Castro
APC personnel worked closely with the Owner and Design Engineer
A&M Consulting Engineers throughout the project. Early on, it was
determined that the City’s water system had several leaking valves
within the work zone. On short notice, W. M. Lyles Co. assisted with
the removal and replacement of the leaking valves. The City had
planned for a separate project to resurface the roadway within the
project limits; however, a change order was successfully negotiated
for APC to grind the existing pavement and place a 2” asphalt
APC joined WML for this Wastewater Treatment
Plant Project.