115113 - Lyles Construction - NEW Newsletter - PROOF - Flipbook - Page 3
WML SOUTHERN DIVISION
Regional Water Recycling Plant No. 5 (RP-5) Liquids Treatment Expansion to
22.5 MGD and SolidsTreatment Facility (Continued from Front Cover)
CHINO HILLS, CA
Of the total 54-month project duration, WML recently hit
the 27-month mark in October 2022. With 22 months of
construction complete, the project hit 50% cost completion in
the same month. Some key highlights of work completed thus
far include: 280,000 CYS of earthwork has been performed;
38,000 CYS of concrete out of the 53,000 CYS project total
have been placed, along with 10.4 million pounds of reinforcing
steel and 300 tons of structural steel; 75,000 SF of structure
shoring has been set; 43,000 LF of underground yard piping
has been installed and 85% of all electrical ductbank is
complete; architectural masonry of seven new buildings has
been completed and exposed electrical, fire protection and
HVAC work is well underway. The project has employed an
average of 200 field craft employees on-site daily.
these challenges, in coordination with subcontractors, the
team employed creative strategies to keep crews actively
progressing the project by strategically sequencing work to
stay in front of challenges to the schedule. The team has
done everything possible to mitigate delays and cost impacts
and is currently delivering a profitable project, on time.
WML Project Team
Project Executive: Juan Ahumada
Project Managers: Stephen Henning, Tyler Vanderzee and
Jason Radliff
Project Engineers: Danny Flores, Alicia Silvas-Porter, Isaiah
Andrade, Charles Henley, Ivette Ayon, Noe Rodriguez and
Ernie Cortez
The project team has completed an astonishing amount of work Field Engineers: Arturo Gomez, Armando Cayama, Jack
over the past year, overcoming unprecedented challenges Saulovich and Nav Bhopal
due to industry-wide bottlenecks caused by a worldwide Project Coordinators: Carol Sanchez and Nicole Ingram
pandemic and its resulting supply chain issues. Lead times Commissioning Engineers: Vijay Kumar and Sam Parkinson
drastically increased without notice and material prices
Superintendents: Mark Glaszczak, Kyle Garner, Armando
skyrocketed. Design issues and changes also overwhelmed
Corona, Anthony Pilato, David Kennedy, Jaime Quintero and
our staff with adjustments to scope and delays. Despite all
Mike Dragoon
1