115113 - Lyles Construction - NEW Newsletter - PROOF - Flipbook - Page 4
EAST COUNTY ADVANCED WATER PURIFICATION PROJECT
SANTEE, CA
WML celebrated the June 1st Groundbreaking Ceremony for
the East County Advanced Water Purifications Program
AECOM DB Team
Design Leads: Jim Mitchell, Brian Harrington and Douglas McClellan
PACKAGE #3
PACKAGE #1
The East County Advanced Water Purification Project Package
1 is a progressive design-build project to construct a water
treatment plant consisting of a 16 million gallon per day (MGD)
Water Recycling Facility, 11.5 MGD Advanced Water Purification
Facility, Visitor Center, Product Water Pump Station, and Solids
Handling Facility. Once complete the plant will process wastewater
from East County San Diego into drinking water, discharging via
Packages 2 and 3 pipelines/pump stations to Lake Jennings. Once
completed, the project will ultimately replace 30% of the drinking
water supply to East County San Diego. The AECOM/WML team
received the NTP on June 1, 2022 with an anticipated project
completion of July 2026.
The AECOM//WML team received the NTP for this exciting
and challenging project on June 1, 2022, with an anticipated
completion date in July 2026. Innovative construction techniques
and interaction with AWP Package 1 make this a ground-breaking
project for WML. The scope of work consists of 12,000 LF of open
cut 30” PVC and 14” HDPE joint trench pipeline. The open-cut
pipeline connects AWP Package 1 to an existing pump station
east of the project by a 3,500 LF horizontal directional drilled
pipeline that is installed 60’ below the ground surface. The project
also includes upgrades to the existing East Mission Gorge Pump
Station and Influent Pump Station, a 10,745 LF slip line pipeline
that will insert a new 20” pipe through an existing 24” pipeline and
will be built within active pump stations, Santee Lakes Recreational
Facility and Fanita Parkway.
WML Project Team
Project Executive: Mike Munden
Project Managers: Mark Moreno (Pump Station & CM) and John
Mabon (Pipeline)
Field Engineers: Parker Jacobs and Matt McBride
Superintendent: Hector “Rod” Rodriguez
AECOM DB Team
Design Lead: Gabriel Perigault
Pipeline Lead: Craig Smith
WML Project Team
Project Executive: Mike Munden
Project Managers: Jeff Tholen (Solids Handling Facility),
Marcos Reyes (Water Reclamation Facility), Bryan Case (Advanced
Water Facility), Tim Holley (Vistors Center)
Project Engineers: Mark Glaszczak, Gabe Ortega, Jaime Quintero,
and Armando Corona
Field Engineers: Yousef Alnajjar, Tim Hobbs, Jack Saulovich
Superintendents: Mark Glaszczak, Gabe Ortega, Jaime Quintero,
and Armando Corona
New launder cover and scum tipping trough at Secondary
Clarifier No. 1. Inland Empire Utilities Agency
2