Broughton Countryside Apartments 2 - PDF best quality - Portfolio - Page 19
Broughton Countryside Apartments 2
VIDEO - FRONT
VIEW OF
WHOLE
In total, there will be six timber-framed blocks, two blocks of each —
three, four and five storeys with apartments. The building required
an innovative solution that we were more than happy to provide.
The development was on either side of the fire-damaged Church of
the Ascension, with three apartment blocks on each; the scheme
also included 197 parking spaces.
Each plot was to feature two L-shaped blocks to either side and a
rectangular block in the middle, with the side closest to the church
being four storeys, stepping up to five, then six towards the outside.
Designed in-house by Countryside
Living, the project represents the
fifth phase of the masterplan area
set out by Salford City Council and Countryside that started
development in 2005.
Building works commenced in September 2018, covering two
parcels of land on Clarence Street in Broughton.
Following groundworks, we provided scaffolding for the timberframed construction, a specialism of ours, from April 2019 for a
duration of 12 months.